Chesterfield Power Station Project Summary – Chesterfield Energy Reliability Center (CERC) Project

In January 2018, Dominion Energy stopped using their two coal-fired boilers #3 and #4 and shut them down on March 31, 2019. Coal boilers #5 and #6 were shut down on May 31, 2023.  The facility no longer combusts coal in any units.

DEQ received revised Prevention of Significant Deterioration (PSD) permit applications for the CERC project on August 1, 2023 and March 3, 2025. Dominion is seeking a PSD permit for a simple-cycle electrical generating station to be located on the site of the Chesterfield Power Station. Dominion states the purpose of this project is to “support the clean energy transition while optimizing reliability and economics” for their system customers.

Proposed equipment:

  • Four 250 MW simple-cycle combustion turbines, capable of combusting natural gas, natural gas with hydrogen (up to 10%), and low sulfur #2 distillate fuel oil.
  • Seven 3,500 kW black start generators firing ULSD.
  • Several circuit breakers, using SF6 as an insulating gas.
  • Eight fixed-roof fuel oil storage tanks (one 12 million gallons and seven 3,500 gallons)
  • Fugitive emissions from piping components

Proposed emissions from facility (tons/year):

PM

PM10

PM25

SO2

NOx

CO

VOC

Pb

H2SO4

CO2e

81.8

153.9

153.9

27.8

353.3

825.3

162.5

0.063

18.7

2.2 million

Turbine emission include startups and shutdowns (firing both natural gas or fuel oil)

The facility is already considered a major source of HAP emissions. The proposed annual HAP emissions from this project: Maximum individual HAP, 5.07 tons of formaldehyde, Total HAP: 13.5 tons.

Proposed permitting timeline: Permitting Enhancement and Evaluation Platform (PEEP)

CERC-related documents available for download: 

 Document Title  Date
 Dominion Energy, Inc. Presentation - CERC  July 2023
 Air Permit Application - CERC  August 2023
 DEQ Initial Letter of Determination  August 2023
 Public Notice of Public Information Briefing  November 16, 2023
 Chesterfield County Zoning Letter  June 2024
 (Espanol) Carta a SCC y DEQ de Chesterfield Co  junio de 2024
 DEQ Zoning Letter Response  July 2024
 Carta a Joseph Casey  julio de 2024
 CERC Application Supplement: Relocation  August 2024
 DEQ Review of Supplemental Information  September 2024
 DEQ Response to Request for Extension  September 2024
 Dominion Response Regarding Revised Site Suitability  September 2024
 DEQ Review of Additional Information  October 2024
 Updated Air Permit Application - CERC  March 2025
 DEQ Acknowledgement/Review Letter  March 2025
 Article 6 Air Quality Impact Analyses - CERC Report  June 2025
 PSD Air Quality Impact Analyses Report - CERC  June 2025
 Public Notice of Public Information Briefing   August 7, 2025
 CERC PowerPoint Presentation - DEQ Public Briefing  August 7, 2025
 Presentación: Centro de Confiabilidad Energética de Chesterfield Reunión informativa pública del DEQ  7 de agosto de 2025
 CERC PSD Fact Sheet  August 7, 2025
 Hoja informativa: CERC (Espanol)  7 de agosto de 2025
 Public Notice of Public Comment Period (August 8 to October 8, 2025) and Public Hearing on September 8, 2025 (Dominion Energy)  September 8, 2025
 DEQ Public Notice of Public Comment Period (August 8 to October 23, 2025) and Public Hearing on October 8, 2025  August 8 to October 23, 2025 &
October 8, 2025
 CERC Permit Application  August 8 to October 23, 2025
 CERC Permit Application Appendices  August 8 to October 23, 2025
 CERC Draft Permit  August 8 to October 23, 2025
 CERC Draft Engineering Analysis  August 8 to October 23, 2025
 Aviso público del DEQ sobre el período de comentarios públicos (del 8 de agosto al 23 de octubre de 2025) y audiencia pública el 8 de octubre de 2025  del 8 de agosto al 23 de octubre de 2025 & 8 de octubre de 2025
 Transcript of CERC Public Hearing  September 2025
 CERC Summary of Public Comment and DEQ’s Responses  November 25, 2025
CERC Resumen de los comentarios públicos y las respuestas del Departamento de Calidad Ambiental (DEQ)  November 25, 2025
 Public Notice – Summary of Comments Public Hearing for Chesterfield Energy and Reliability Center (CERC) Project  December 10, 2025
 Aviso Público – Resumen de Comentarios Audiencia Pública Centro de Fiabilidad de Chesterfield   10 de diciembre de 2025
 CERC Prevention of Significant Deterioration Permit  December 19, 2025
 CERC Engineering Analysis  December 19, 2025


For questions regarding this project, please contact Alison Sinclair at (804) 489-1008.