For the closure of Pond D, Dominion has proposed to excavate and move all CCR currently in Pond D to a newly constructed landfill located on the Possum Point facility property. Dominion has submitted a solid waste permit application to DEQ, but a permit has not yet been issued.
Possum Point Power Station is defined as a public facility in the Prince William County Zoning Ordinance. In March 2022, Dominion submitted a request to Prince William County’s Planning Office for a public facilities review determination for a proposed CCR landfill at Possum Point. Prince William County concluded that: "...the proposal does not substantially change the location, character, and extent of the Possum Point Power Station facility, and is exempted from the requirement for a [public facility review]."
Letter from Prince William County to Dominion responding to public facility review determination request.
[link will open a Prince William County government page]
In October 2022, Dominion submitted a solid waste permit Part A application to DEQ. DEQ provided technical review comments on the Part A application in December 2023 and received a response to the comments in March 2024. As a condition of obtaining a landfill permit, Dominion is working with Prince William County to offer and provide municipal water supply and residential service connections to properties not currently served that are within one mile of the proposed landfill (§ 10.1-1402.05). DEQ issued a conditional approval of the Part A application in May 2024.
Part A Processing Documentation:
Dominion submitted the solid waste permit Part B application to DEQ on December 27, 2024, and the permit application status can be tracked using the Permitting Enhancement and Evaluation Platform (PEEP) on the DEQ website using PEEP Request Number SWP628. DEQ issued a completeness review letter on January 31, 2025, and Dominion submitted a response with additional information on March 7, 2025. DEQ issued a letter on April 4, 2025, stating that the Part B application appeared to be administratively complete and that DEQ would begin technical review. DEQ issued a technical review letter on July 31, 2025, and Dominion submitted a response with additional information on September 22, 2025. DEQ issued a second technical review letter on November 21, 2025, providing comments on the revised Part B application. A response from Dominion is anticipated in January 2026.
Part B Processing Documentation:
In addition to the solid waste permit, the reissuance of the existing Virginia Pollutant Discharge Elimination System (VPDES) permit which authorizes the discharge of industrial process water and industrial stormwater associated with power production and the discharge related to dewatering activities associated with Pond D closure is pending. This reissuance will also include requirements, as appropriate, for discharges of industrial process water and/or industrial stormwater associated with the landfill post construction.
Other required permits include a Virgina Water Protection (VWP) permit for wetland impacts due to the proposed landfill (issued by DEQ in May 2023), and erosion and sediment (E&S) and stormwater construction general permit (SWCGP) from Prince William County (not yet issued but required prior to initiating landfill construction).