Waste Permit Time Frames

Solid waste landfill

  • Part A
    • Completeness review: 30 days
    • Processing of complete application: 90 days (estimated)
    • Public comment: N/A
  • Part B
    • Completeness review: 30 days
    • Processing of complete application: 180 days (estimated)
    • Public comment: 90 days (estimated)

Solid waste treatment and storage

  • Permits-by-Rule
    • Completeness review: 30 days
  • Part A
    • Completeness review: 30 days
    • Processing of complete application: 60 days  (estimated)
    • Public comment: N/A
  • Part B
    • Completeness review: 30 days
    • Processing of complete application: 120 days  (estimated)
    • Public comment: 90 days  (estimated)

Yard waste composting

Regulated Medical Waste Full (Off-Site) Permit-by-Rule

  • Permits-by-Rule
    • Completeness review: 30 days (estimated)

Regulated Medical Waste On-Site Permit-by-Rule and Yard Waste Composting Permits-by-Rule

Effective upon filing complete application and required information.

Hazardous waste

  • Treatment and storage
    • Completeness review: 60 days
    • Processing of complete application: 120 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Land disposal
    • Completeness review: 60 days
    • Processing of complete application: 250 days
    • Public comment: 135 days*
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Incineration: Trial burn
    • Completeness review: 60 days
    • Processing of complete application: 250 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Incineration: Final
    • Completeness review: 60 days
    • Processing of complete application: 120 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Emergency permit
    • Completeness review: 5 days
    • Processing of complete application: 10 days
    • Public comment: 30 days *
    • Remarks: * Public notice occurs after permit issuance.
footer divider
footer divider
footer divider
Virginia Department of
Environmental Quality
P.O. Box 1105
Richmond, VA 23218
(804) 698-4000


Some resources on this website require Adobe Reader and Flash Player, Microsoft Word, PowerPoint or Excel. If you wish to receive this content in an accessible format pursuant to Section 508 of the federal Rehabilitation Act of 1973, as amended (29 U.S.C. ยง 794 (d)), please call 800-592-5482. In addition, this website includes hyperlinks to websites neither controlled nor sponsored by DEQ or the Commonwealth of Virginia. Links may open in a new window. If you wish to receive content from a website which is neither controlled nor sponsored by DEQ or the Commonwealth, please contact the host of that website directly.