Waste permit time frames

Solid waste landfill

  • Part A
    • Completeness review: 15 days
    • Processing of complete application: 90 days
    • Public comment: N/A
  • Part B
    • Completeness review: 30 days
    • Processing of complete application: 180 days
    • Public comment: 90 days

Solid waste treatment and storage

Time frames apply to full permits only. Certain permits-by-rule become effective upon submittal of the required information, others become effective when DEQ acknowledges receipt of the required information.

  • Part A
    • Completeness review: 15 days
    • Processing of complete application: 60 days
    • Public comment: N/A
  • Part B
    • Completeness review: 30 days
    • Processing of complete application: 120 days
    • Public comment: 90 days

Yard waste composting

Effective upon filing complete application and required information.

Hazardous waste

  • Treatment and storage
    • Completeness review: 60 days
    • Processing of complete application: 120 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Land disposal
    • Completeness review: 60 days
    • Processing of complete application: 250 days
    • Public comment: 135 days*
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Incineration: Trial burn
    • Completeness review: 60 days
    • Processing of complete application: 250 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Incineration: Final
    • Completeness review: 60 days
    • Processing of complete application: 120 days
    • Public comment: 135 days *
    • Remarks: * Includes 60 days for EPA review and 45 days for public comment.
  • Transportation
    • Completeness review: 3 days
    • Processing of complete application: 7 days
    • Public comment: N/A
  • Emergency permit
    • Completeness review: 5 days
    • Processing of complete application: 10 days
    • Public comment: 30 days *
    • Remarks: * Public notice occurs after permit issuance.